Bayou Vermillion Flood Control Project

Customer - Lafayette Consolidated Government

Location - Lafayette, LA

RIGID developed and executed a 24/7 work schedule to excavate, haul, and place over 1,000,000 cy per month, completing the 6M cy of excavation in under 6 months.

Utilizing specialized company-owned mass excavation equipment, RIGID was able continue production even under wet weather conditions. Quad Tracks and Motor Graders were used to maintain haul roads, and off road Haul Trucks were equipped with low ground pressure tires.